Scope

Design South was retained to evaluate and update Clemson University’s existing Campus-wide Stormwater Master Plan.  Review of the existing information revealed that the current master plan had a heavy emphasis on stormwater modeling and needed to be updated to bring the University into compliance with the new Municipal Separate Storm Sewer System (MS4) regulations.
Scope:

  • Review of existing stormwater plan
  • Review of NPDES Municipal Separate Storm Sewer System (MS4) Permit
  • Development of a comprehensive Stormwater Master Plan for Clemson University’s Main Campus in anticipation that Clemson University will be designated an MS4
  • Preliminary development and Stormwater Master Plan deployment

Key Facts

Location
Clemson, South Carolina
Client/s
Clemson University
Project Type
Stormwater
Cost
Phase 1 $26,300